Siemens SICHARGE UC Installation And Commissioning Manual page 74

Hide thumbs Also See for SICHARGE UC:
Table of Contents

Advertisement

Finishing the flooring - (Responsibility of civil engineering company)
No.
1
Use suitable protection methods to protect metal parts (such as rods, nuts and washers) from
corrosion and damage
2
Fill the space underneath the mast base with fine-grained concrete
3
Install suitable protection materials before you fill in the concrete around the mast base
4
Fill in the area around the SICHARGE UC MastPanto with the substructure required for the flooring
5
Finish the flooring
6
Make sure to sign this document at the end of this checklist.
① Threaded rod and nuts
② Protective sleeve for threaded rods
③ Foundation
Figure 6-11
Comments and findings:
-
-
-
-
-
-
-
-
-
-
-
Responsible person
(optional) Customer
Please take into consideration that the document is only valid after signatures of technician or if included in the final
document delivered to the customer.
Installation and Commissioning Checklist for SICHARGE UC
Product Information, 03/2023, A5E52548271-AA
Checklist item
Final work MastPanto
Name
④ Protection material
⑤ Fill material
⑥ Flooring
Function
SICHARGE UC MastPanto
6.3 Connection
P
F
N/A
Signature
73