SICHARGE UC MastHood
5.4 Commissioning
Reconnect the vehicle
No.
1
Disconnect the Hood from EV Panto, wait for 10s and reconnect the plug
2
HMI displays Vehicle Connected, Cable Check, Pre-charge and Charging. The Charger stops when
vehicle requests, no error is displayed on the HMI. No need to record the V2G communication
Comments and findings:
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Responsible person
(optional) Customer
Please take into consideration that the document is only valid after signatures of technician or if included in the final
document delivered to the customer.
54
Checklist item
Name
Function
Installation and Commissioning Checklist for SICHARGE UC
Product Information, 03/2023, A5E52548271-AA
P
F
N/A
Signature