13.4.4

Loading the HW config to NCU

Introduction
The newly created network configuration PG/PC must be introduced to NCU.
You have established a connection to the Ethernet interface (X120 or X127) and you load
this configuration from the PG/PC to the NCU using the operator-input sequence steps laid
out below.
Operator input sequence steps for loading HW config to NCU
1. Change from "NetPRO" to "HW Config".
2. Press the "Download to module" button.
3. Confirm the load into the module with "OK".
4. Confirm the dialog boxes displayed subsequently with "OK" or "No" for the query
IBN CNC: NCK, PLC, drive
Commissioning Manual, 07/2007, 6FC5397-2AP10-3BA0
The target module interactive screenform automatically displays both configured
communication peers.
"...Should the module be started now (restart)?".
Note
Loading the HW config to NCU is only possible via Ethernet interface.
13.4 Integrating PG/PC into the network (NetPro)