The following example releases BB#11 from the system and initializes it.
XSCF>   initbb -b 11
You   are   about   to   initialize   BB/XB-Box.
NOTE   the   following.
1.   BB/XB-Box   is   excluded   from   the   system   and   halted.
2.   PPAR-ID   of   the   same   value   as   BB-ID   becomes   invalid.
Continue?   [y|n]   : y
Note - After the execution of the initbb command, the target chassis is released from the
system and enters the stopped state. Do not disconnect the power cords or various cables
until the XSCF STANDBY LED on the panel and the rear READY LED of the target chassis
are off.
8.
Execute step 7 on each chassis of the SPARC M10-4S to be removed.
9.
Confirm that the LED of the SPARC M10-4S to be removed is off, and then
disconnect all the power codes of the chassis from the input power.
10. Disconnect the cables that pass between the racks.
Crossbar cables passing between the racks are laid using the spiral tubes.
Remove the tube of the side of the expansion rack 1, and lay it in the tube of the
side of the expansion rack 2.
11. Disconnect the expansion rack 1 from the expansion rack 2.
Disconnect the racks in the reverse order at the rack connection. For the
procedure for the rack connection, see
12. Remove the XSCF-BB control cables from the target SPARC M10-4S on the
expansion rack 1.
13. Remove the crossbar cables from the target SPARC M10-4S on the expansion
rack 1.
14. Remove the target SPARC M10-4S from the expansion rack 1.
Remove the SPARC M10-4S from the rack by reversing the mounting procedure.
For the procedure for mounting in the rack, see
M10-4/SPARC M10-4S in a
Chapter 10 Removing a System with a Building Block Configuration