Step 2 Turn the AC input switch to ON.
Step 3 Observe the annular strip light. If all green lights are steady on, battery charging is
complete.
Step 4 After the charge is complete, turn off the upstream AC input circuit breaker of the
iSitePower-M system and then the DC SWITCH. Hold down the manual ON/OFF
switch for 5s to shut down the battery module. If other batteries need to be
charged, repeat the preceding steps.
----End
Issue 02 (2021-12-30)
If there is PV input, turn on the DC SWITCH.
If there is no PV input, hold down the manual ON/OFF switch for 5s.