6.10 Checking After Commissioning

Check Item
The thermal insulation foam of the copper pipes and
the bottom plate are free of oil stains and are clean.
The needle valve plug is secured (torque of 0.45±0.05
N·m), and the valve bonnet is tightened. The needle
valve thermal insulation foam is restored.
The foreign matter on the water pan and bottom plate
is cleaned up.
The air filters are correctly installed according to the air
flow direction on the frame.
Issue 04 (2022-12-15)
Copyright © Huawei Digital Power Technologies Co., Ltd.
6 Power-On Commissioning
Check Result
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed