2. Workflow to install a YSP10

Start
Bring in the machine to the installation site (page 13)
Remove shipping brackets (page 14)
Confirm and connect the solvent tank (page 21)
Install accessories packaged with the machine (page 24)
Connect the power cable and air hose to the machine (Page 28)
Power on the machine and perform return-to-origin (Page 30)
Line alignment procedures (page 35)
Connect board transfer signal lines and check their connection (page 46)
Board transfer test (page 51)
Install the air conditioning unit (optional) (page 52)
Adjustments after installing YCP10 (page 62)
Procedures after installation and adjustment work (page 115)
SI1906002E-001=YSP10 installation and adjustment procedures