Application Turnover Check List; Software Configuration Checks - GE Vivid T8 Basic Service Manual

Hide thumbs Also See for Vivid T8:
Table of Contents

Advertisement

General Procedures and Functional Checks

4-5 Application Turnover Check List

4-5-1 Software Configuration Checks

Step
1
Verify Date and Time is correct.
2
Verify that Location (Hospital Name) is correct.
3
Verify Language settings are correct.
4
Verify assignment of Print Keys.
5
Verify all of the customer's options are set up
correctly.
4-38
Complete these checks before returning the scanner to
customer for use:
Table 4-4:
Software Configuration Checks
Task to do
Demo Option strings turn on
Vivid T9/Vivid T8 – Basic Service Manual
5795591-100 English Rev. 3
Notes