4.4.12 Replacing Batteries for the VESDA Power Box

Prerequisites
Spare VESDA power box batteries of the same model are available and functional.
Impact on the System
None
Preparations
Tools: Phillips screwdriver, protective gloves
Materials: spare VESDA power box batteries
Documents: fire extinguishing device layout diagram (standard)
Skill requirement: fire engineer
Procedure
Step 1 Move the VESDA power box batteries to the installation position indicated on the fire
extinguishing device layout diagram.
Step 2 Switch off the standby power supply for the VESDA.
Figure 4-42 Switching off the standby power supply