Step 3: Wire the SVI FF
Perform wiring as per Figure 8.
I/P Connector
Configuration Lock
Jumper
9 - 32 V
Foundation Fieldbus
Input Signal
(polarity independent)
Shield
(on FF unit
housing)
Figure 8 Connections to Electronics Module (via Terminal Board)
NOTE
Step 4: Set Tag and Address
Using NI Configurator as an example:
1. Import DD/CFF files.
CAUTION
2. Right-click on the device, select Set Tag, follow the prompts to enter a Tag.
3. Click Set.
32 |
BHGE
AI PV 1-5 VDC (Not Used in this release)
Refer to FOUNDATION Fieldbus instructions for shield connections
on the FF H1 bus.
Do not navigate to the NI DD folder and copy the DD file onto itself.
Discrete Out
Display
© 2019 Baker Hughes, a GE company, LLC. All rights reserved.
Discrete Input
Remote
Position
Sensor
Input