DD Method

This section shows an example using the Invensys EVO. The screens may change a bit
between programs, however, the text that appears will not. The objective of this procedure is
to set the unit to Normal mode so that the TB block is changed from LO mode to Normal.
1. Open the DD host program and navigate to and select the positioner, right-click and select
Methods > change app mode.
It is important to note that the mode indicates Setup on the DD screen. This is what
appears even when the positioner in LO mode.
2. Ensure Yes ()is shown in Figure 105, then click Go and Figure 106 appears.
256 |
BHGE
Figure 105 Initial Mode
Figure 106 Mode Selection
© 2019 Baker Hughes, a GE company, LLC. All rights reserved.