28 Installation checklist
Electrical installation
1.
Types and cross-sections of control cables suitable for the signal type and signal level
2.
Types and cross-sections of power cables selected according to the
Guideline
3.
Pulse encoder cable screens connected to screen grounding point and not connected directly
to the pulse encoder interface (only applicable for drives with pulse encoder interface)
4.
Internal cabling to integrated transformer (power, auxiliary, control and heater cables) made
according to the instructions in this manual (Chapter
5.
Cable entry made according to the instructions in this manual (Chapter
6.
All control cable screens and conductors are connected according to the instructions in this
manual (Chapter
connections are completed
7.
Heating cable (if supplied) installed according to the instructions in this manual (Chapter
Electrical
installation)
8.
Ground cable of drive securely connected at both ends
9.
Input and motor cables not connected at both ends (cables must be meggered before
connection, drive optional - recommended in case of long storage time, humid environment or
visible transportation damages)
Door interlocking
1.
Door locks tested and in operation
2.
The manual release of the door safety switch(es) is in the locked position.
Main circuit breaker (MCB)
1.
Type of MCB selected as per
2.
High voltage connections completed
3.
MCB ready to be tested with drive
Electrical
installation)
, appropriately labeled, and the customer-side
ACS580MV Engineering Guideline
ACS580MV Engineering
Electrical
installation)
Electrical
installation)