Install an A-240Z-A CPE
52
 
7
If applicable, install the power supply according to manufacturer specifications.
Note —
Observe the following:
Units must be powered by a Listed or CE approved and marked
limited power source power supply with a minimum output rate of
12 V dc, 1.25 A.
8
Power up the CPE unit by using the power switch.
9
Verify the CPE LEDs and voltage status; see the 7368 Hardware and Cabling Installation
Guide.
10
Activate and test the services; see the 7368 Hardware and Cabling Installation Guide.
11
If necessary, reset the CPE.
i
Locate the Reset button on an A-240Z-A CPE as shown in Figure 13.
ii
Insert the end of a straightened paper clip or other narrow object into the hole in the
Reset button to reset the CPE.
12
STOP. This procedure is complete.
3FE-46615-AAAA-TCZZA
7368 ISAM CPE A-240Z-A Product Guide