Step 1 Determine a position for installing the pRRU on a wall, use a level to verify that the marking-
off template is placed horizontally, and then use a marker to mark anchor points, as shown in
Figure
Figure 9-7 Marking anchor points
(1) Level
Step 2 Drill holes at the anchor points and install expansion bolts in the holes, as shown in
9-8.
Issue 06 (2015-10-30)
9-7.
(2) Tapped hole
NOTE
It is recommended that the separate mounting kit be 1200 mm (47.24 in.) to 1600 mm (62.99 in.) above
the ground.