Operations Counter; Final Tasks - GE GL 310 F3/4031 P/VR Operating Instructions Manual

High voltage circuit breaker
Table of Contents

Advertisement

C
OMMISSIONING
7.6.10

Operations Counter

7.6.11

Final Tasks

56
• Check the operation of the operations counter.
• Read the count shown on the counter and enter the values in the
checklist.
• Remove all testing and measuring equipment from the circuit
breaker.
• Replace the roof and side panels of the mechanism after work is
completed. Tighten the bolts (6) and nuts (5) to a torque of 17Nm.
• Clean up the installation site.
The breaker is ready to be connected to the high voltage system.
OI 248 (EN)
REV6
/REV7