8.2. Commissioning checklists
The checklists are designed to help you prepare the drive and associated equipment
for commissioning.
8.2.1. Mechanical installation checklist
1) Drive installed according to the instructions in this user manual (3BHS206977
E01).
2) Drive securely fastened to the floor (if applicable).
3) Redundant fan unit installed (if applicable).
4) Visual inspection:
•
No badly affixed or damaged components
•
No foreign objects left in the cabinet
•
No dirt, dust or moisture in the cabinet
8.2.2. Electrical installation checklist
1) Types and cross sections of control cables suitable for the signal type and signal
level.
2) Types and cross sections of power cables selected according to the instructions
in this user manual (3BHS206977 E01).
3) Pulse encoder connected according to the relevant manual (only applicable for
drives with pulse encoder interface).
4) Cable entries prepared according to the instructions in the user manual
(3BHS206977 E01 J).
5) Control cable screens and conductors are connected as instructed in the user
manual, labeled appropriately, and the customer side connections are completed.
6) Equipotential bonding conductor of drive securely connected at both ends.
7) Converter transformer and motor cables not connected at both ends (cables and
drive must be insulation resistance tested (Megger test) before connection)
PRODUCT
ACS1000i
DOCUMENT KIND
User manual
DOCUMENT ID.
3BHS206977 E01
COMMISSIONING
REV.
LANG.
PAGE
J
en
88/146