46
en | How to Install Reader and Field Devices
6.7
Field devices using I/O board
This will provide the system installer to have the flexibility of configuring any input in the panel
to be in any monitoring requirement. The following diagrams shows wiring diagram for 2 State
Non-Supervised, 2 State Supervised and 4 State Supervised input points.
6.7.1
Wiring Diagram for 2 State Supervised Input points
NORMALLY OPEN
INPUT POINT
NORMALLY CLOSED
INPUT POINT
Ver 2.0.0 | 2006.07
6.8K Ohm
6.8K Ohm
T8
Hardware Manual
T7
1
JP2
CN1
CN2
Access Easy Controller
T6
T2
1
T3
T4
T5
1
T1
Bosch Security Systems