Start-up and operation
Contents of this chapter
This chapter describes the start-up procedure of the PVS-100/120 medium voltage station
(MVS) and the general operation criteria.
WARNING!
Only an authorized electrician is permitted to install the cabling to the MVS. Obey
the
Safety instructions (page 9)
physical injury or death, or damage to the equipment may occur.
WARNING!
Do not do electrical installation work during a thunderstorm.
Tools needed
•
Voltage detector
•
Insulation resistance meter. For more information, see section
resistance of the cabling (page
•
Personal protective equipment
Prerequisite
WARNING!
Use original silica gel bags only during transport. Install new silica gel bags for
storage.
1. Remove the transportation covers.
and the local safety regulations. If ignored,
43).
Start-up and operation 51
7
12
Measuring the insulation