Lifting

WARNING!
Inspect the container before any activity. Make sure that the container has no
protuberance, enough rings and is in good condition. Ignorance of this message
can cause physical injury, death or damage to the equipment.
Before lifting the MVS, follow these instructions.
Protect the corners of the MVS against shock.
The minimum rated loading capacity of each sling is ten tons
The minimum length of each sling is five meters.
Adjust the length of lifting slings so that the MVS does not tilt during lifting.
Do not allow the lifting slings to scratch the walls or roof. Damaged paint can lead to
corrosion.
Use a guide wire attached to a lower corner of the MVS to prevent rotation.
Do not throw slings or hooks onto the roof.
Do not stand on the roof during fastening the lifting slings or lifting.
Before loading, make sure that nobody is present under the load.

Tools used for lifting

20 tons bridge crane or 70 tons truck crane
four slings
Forklisft
Storing, lifting and transporting 29