Hardware Installation

1
Installing the Cabinet
1. Determine the cabinet position based
on the engineering layout diagram.
2. Place the cabinet at the correct
installation position.
3. Level the cabinet using a wrench.
Use a measuring tape to check
that the vertical distance between
the top of the 2000 mm high
cabinet and the floor is 2000 mm
(+3 mm). Then use a level to
check that the cabinet is level.
Do not remove the anchor bolts.
Otherwise, rework is required if
the cabinet height does not meet
requirements.
2
Installing a Drainage Pipe for the Smart Cooling Product
1. Remove the baffle plate from the smart cooling product.
2. Cut the rubber plug of the water pipe hole at the bottom of the cabinet and route the
drainpipe.
3. Install the baffle plate for the smart cooling product.