Figure 21.
Lifting HRU (1)
[Rear Side]
2
3
5G NR HRU Installation Manual v1.0
Copyright © 2018, All Rights Reserved.
Carrying Point_1
For Eye Bolt
Carrying Point_2
For Handle
While Operator A hauls the rope to carry up the HRU, Operator B pulls the
rope outward, so that HRU would not hit the tower platform.
Operator C locates the carried HRU to the installation position.
Confidential
Chapter 2 Installing System
Carrying Point_1
For Eye Bolt
[Rear Side]
25