Installation and commissioning flowchart

Identify the frame size of your drive: A, B, C or D.
Plan the installation.
Check the ambient conditions, ratings, required
cooling air flow, input power connection, compatibility
of the motor, motor connection, and other technical
data.
Select the cables.
Unpack and check the units.
Check that all necessary optional modules and
equipment are present and correct.
Only intact units may be started up.
Check the installation site.
If the drive is about to be connected to an IT
(ungrounded) system, check that the screw(s)
labelled VAR are removed. Also note that using a
mains filter is not allowed in an IT (ungrounded]
system.)
Install the drive in a cabinet.
Route the cables.
Check the insulation of the supply cable, the motor
and the motor cable, and the resistor cable (if
present).
Task
See
Technical data: Ratings
(page 71)
Planning the cabinet assembly
Planning the electrical installation
Technical data
(page 71)
Option manual (if optional equipment is
included)
Mechanical installation:
Contents of the
package
(page 31)
If the converter has been non-operational for
more than one year, the converter DC link
capacitors need to be reformed. Ask ABB for
more information.
Mechanical
installation: Before installation
(page 33)
Technical data
(page 71)
Safety
instructions:
Installation and
maintenance work
(page 6)
Mechanical
installation:
Installation procedure
(page 34)
Planning the electrical
installation:
cables
(page 44)
Electrical installation:
Checking the insulation of
the assembly
(page 47)
17
(page 25)
(page 37)
Routing the
About this manual