Before installation

Delivery check

The drive delivery contains:
• drive cabinet line-up
• optional modules (if ordered) installed into the control rack at the factory
• ramp for extracting supply and inverter modules from the cabinet
• hardware manual
• appropriate firmware manuals and guides
• optional module manuals
• delivery documents.
Check that there are no signs of damage. Before attempting installation and
operation, check the information on the type designation label of the drive to verify
that the unit is of the correct type. The label includes an IEC and NEMA rating, C-UL
US, and CSA markings, a type designation and a serial number, which allow
individual recognition of each unit. The first digit of the serial number refers to the
manufacturing plant. The next four digits refer to the unit's manufacturing year and
week respectively. The remaining digits complete the serial number so that there are
no two units with the same serial number.
The following type designation label is located on the supply unit door.
In addition to the actual type designation label, there are the following two labels
attached elsewhere on the drive.
Each power module (ie, supply and inverter module) is also individually labelled.
Mechanical installation