8/11K Va 1Phase - Lenovo RT8.0kVA Installation And User Manual

6u rack or tower ups
Hide thumbs Also See for RT8.0kVA:
Table of Contents

Advertisement

8/11k VA 1Phase

Procedure
1. Remove the top cover
removing the 3 screws.
2. Punch the knockouts of the MBP I/O UPS connection cover
2 provided conduit fittings inside.
3. Insert the provided conduit with blue color coding
NORMAL AC SOURCE conduit fitting.
Note: Take care to leave the conduit end with blue label on opposite side (for
connection to UPS).
4. Connect the 3 wires of this blue color conduit
AC SOURCE MBP terminal blocks.
5. Insert the provided conduit with red color coding
UPS OUTPUT conduit fitting.
Note: Take care to leave the conduit end with red label on opposite side (for
connection to UPS).
6. Connect the 3 wires of this red color conduit
MBP terminal blocks.
7. Put back the MBP I/O UPS connection cover
on the MBP casing.
8. Put back the top cover
secure it with 3 screws.
9. Remove the I/O terminal blocks cover of the UPS.
of the MBP I/O UPS connection cover
to the FROM UPS OUTPUT
of the MBP I/O UPS connection cover
Chapter 4. Power cables connection
after
and insert the
, through the TO UPS
to the TO UPS NORMAL
, through the FROM
and secure it with 4 screws
and
31

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rt11.0va

Table of Contents