Please note:
• Mount the corresponding
WT workpiece pallet
before confi guring the
lifting speed (operating
load).
• Try to confi gure the HQ to
lift evenly and smoothly.
Throttle the supply
air evenly using both
throttles to adjust the
speed of the lifting
movement.
• Rotate in the "+" direction
The movement is slower.
• Rotate in the "–" direction
The movement is faster.
8.3 Re-commissioning after a standstill period
Follow the steps outlined for the initial start-up.
8.4 Setting the lifting speed
Sudden movements
Risk of serious injury or death.
Final commissioning may only be performed with protective devices in place.
These must be provided and installed by the customer.
X
Fig. 20:
Setting the lifting speed (example shown here on HQ 5/XH)
WARNING
–
+
3 842 558 544/2017-07, MIT: HQ 5/H, HQ 5/XH, Bosch Rexroth AG
Start-up
37/60
Y
557 617-21