Installation
7.3 Connecting SITOP BAT1600 battery modules to the UPS module
Commissioning the SITOP BAT1600 battery module
Figure 7-3
1. When supplied, LiFePO4 batteries are internally disconnected and therefore must first be
connected.
2. Insert fuse ③.
3. For 3.2 Ah and 12 Ah devices: Move the fuse cover over the fuse until it latches into place.
4. Connect power ① and communication connectors ② to the SITOP UPS1600. Carefully
check that the wiring polarity is correct!
5. Plug-in the connector at the battery module and commission the system.
After approximately 5 s battery module SITOP BAT1600 is detected by the SITOP UPS1600.
214
Power terminals
Communication terminals
Commissioning
SITOP UPS1600 / BAT1600 / UPS1100
Equipment Manual, 07.2021, A5E37775406-11-76