Virtual keyboard
2. Enter the PV power connected
3. Press OK
4. Enter the limit for input active power at the grid
connection point
In this field, enter the value of the input active
power of the generator units (inverters)
connected that is to be reduced. Also check the
required input limits of all generator units
connected to the grid connection point. The input
limits may be different depending on the year of
commissioning. The total of all the input power
values to be reduced must not exceed that of the
storage system.
5. Press Next
The input active power is limited.
8.8

Completing commissioning

Prerequisites
The Confirmation window is open.