DANGER
WARNING
Bosch Power Tec GmbH
8

Commissioning

Risk of fatal injury due to incorrect earthing
If components of the storage system are not earthed
according to the instructions, this can cause electric
shock, which can lead to serious injury or death.
Before commissioning: Carry out measurements
according to the standard DIN EN 62446
Earth all components of the storage system before
commissioning
Risk of injury due to lack of expertise
Installing and commissioning the storage system
requires training, as well as established expertise in
electrical engineering.
Installation, cabling and commissioning must only
be carried out by authorised, trained electricians
8.1

Switching on the storage system

Prerequisites
Measurements are carried out according to the
standard DIN EN 62446.
Procedure
1. Open the housing door
2. Turn the On/Off switch to On
On/Off switch (1)
8.1:
3. Close the housing door on the storage system
(1)
Storage system | Installation manual
Commissioning | 111