Assembly (Fig. 6)
1. Slide bearing onto cap screws that are inserted into
frame. Secure bearing to frame with four (4) lock nuts
(item 3).
2. Install and tighten locking collar to drive roller shaft
(Fig. 8):
A. Slide locking collar to bearing assembly and drive
roller shaft.
B. Using blind hole in locking collar as an impact
point, lock collar by striking it with a punch in the dir-
ection of drive roller shaft rotation.
C. Apply Loctite #242 (or equivalent) to threads of
set screw. Install and tighten set screw to secure
locking collar to drive roller shaft.
3. On both sides of machine, apply tension to floor con-
veyor belt at idler roller shaft (Fig. 7):
A. Retain tensioner rod with wrench to prevent it
from turning.
B. Tighten adjusting jam nut to apply tension to floor
conveyor belt. If locking jam nut is in original position,
adjusting jam nut can be tightened until locking jam
nut is secure.
C. Repeat for other side of machine. Make sure that
adjustments on both sides of the machine are equal.
4. Lubricate conveyor roller bearings at grease fittings.
5. Secure all removed guards to frame (see Bed
Guards in this section).
IMPORTANT: Before adjusting conveyor belt ten-
sion, check for trapped spreading material between
conveyor bed, belt and rollers. Clean machine as re-
commended in Operator's manual.
6. Check and adjust conveyor belt tension as needed
(refer to Operator's Manual).
ProPass 200
1
2
1. Tensioner rod
2. Locking jam nut
1. Locking collar
2. Set screw
3. Blind hole
2
4
1. Drive roller
2. Idler roller
Page 5 - - 9
4
3
Figure 7
3. Adjusting jam nut
4. Take up bearing
2
3
5
4
Figure 8
4. Drive roller shaft
5. Lock nut (4 used)
FRONT
3
Figure 9
3. LH conveyor frame
4. Rotation direction