● Wear insulated gloves and use insulated tools to prevent electric shocks or
6.1 Verification Before Power-On
Table 6-1 Check items and acceptance criteria
No.
1
2
3
4
5
6
7
8
Issue 10 (2023-02-13)
6
D ANGER
short circuits.
Check Item
SUN2000
WLAN antenna
Cables routing
Cable tie
Grounding
Switch
Cable connection
Unused terminal and port
Copyright © Huawei Technologies Co., Ltd.
System Commissioning
Acceptance Criteria
The SUN2000 is installed correctly and
securely.
The WLAN antenna is installed
correctly and securely.
Cables are routed properly as required
by the customer.
Cable ties are evenly distributed and no
burr exists.
The PE cable is connected correctly,
securely, and reliably.
The DC switch and all the switches
connecting to the SUN2000 are OFF.
The AC output power cable, DC input
power cable, battery cable, and signal
cable are connected correctly, securely,
and reliably.
Unused terminals and ports are locked
by watertight caps.
6 System Commissioning