Section 9
Establishing connection and verifying the IEEE C37.118/1344 communication
IEC140000143 V1 EN-US
Figure 15:
•
Open the capture file and observe the captured synchrophasor data. In order to get the Phasor
names on top of each column (See figure 16), the capture process should start before
connecting the PMU Connection Tester to the PMU, i.e. first start the capturing and then click
Connect.
70
Stop capturing the IEEE C37.118 synchrophasor data
© 2017 - 2021 Hitachi Power Grids. All rights reserved
1MRK 511 403-UEN Rev. K
IEC140000143-1-en.vsd
Bay control REC670
Commissioning manual