Huawei OptiX OSN 6800 Quick Installation Manual page 8

Intelligent optical transport platform, n63b cabinet
Hide thumbs Also See for OptiX OSN 6800:

Advertisement

Installing Subracks and Boards
1 Installing Subracks (Subracks, Two CRPC Boards and Multiple DCM
Frames)
NOTE
For safety concern, at least two persons are required to install a subrack. One person is to hold the subrack and
the other person to tighten the panel screws.
NOTE
Install two CRPC boards and multiple DCM frames to the lower subrack.
83
81
77
76
63
62
61
60
47
46
40
37
36
35
22 21
16
14
12
10
7
6
5
4
3
2
Front
PDU
OptiX OSN 6800
Subrack 3
OptiX OSN 6800
Subrack 2
Air deflector
OptiX OSN 6800
Subrack 1
CRPC
CRPC
DCM
DCM
DCM
5
Installation
Structural
holes on one
component
column
2, 3
DCM frame
4, 5
6, 7
10, 12
CRPC
14, 16
Subrack 1
21, 22, 35, 36
Air deflector
37, 40
Subrack 2
46, 47, 60, 61
Subrack 3
62, 63, 76, 77
TN11PDU
79, 83
DPD63-4-8
81, 83
PDU