4 Installing and Routing Ground and Power Cables to a Subrack
a
Installing Ground Cables
1
Connect one end of the ground cable of each subrack to the bottom-side ground bolt of the subrack and the
other end to an idle ground bolt adjacent to this subrack on the right-side column of the cabinet and use a
screw to secure this end.
2
Connect the ground cables of the PDU in parts A and B to the ground bolts at both sides of the cabinet.
Ground point for the
DPD63-4-8 PDU
27
Phillips screwdriver
Ground cable