Step 1 Lay out a ground cable. Route the ground cable into the power cabinet through a cable hole at
the left bottom.
Step 2 Secure one end of the ground cable to the power cabinet ground bar, and the other end to the
site ground bar.
Step 3 Route an equipotential ground cable into the power cabinet through a cable hole at the left
bottom and into the battery cabinet through a package entry module at the left bottom.
Step 4 Secure one end of the equipotential ground cable to the power cabinet ground bar, and the
other end to the battery cabinet ground bar, as shown in
Issue 01 (2014-03-12)
5

Installing a Ground Cable

Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.