TP48200A-HT19C4-1 & TBC300A-TCA2
Installation Guide
7.4 Installing the TCUA Power Cable
Procedure
Step 1 Lay out the TCUA power cable. Route the power cable into the power cabinet through a cable
hole at the right bottom and into the battery cabinet through a package entry module at the left
bottom.
Step 2 Connect one end of the power cable to the PWR port on the battery cabinet TCUA.
Step 3 Secure the negative terminal on the other end of the power cable to the BLVD circuit breaker
(≥10 A).
Step 4 Secure the positive terminal on the other end of the power cable to the corresponding screws
on the RTN+ busbar, as shown in
Figure 7-9 Installing the TCUA power cable
----End
Issue 01 (2014-03-12)
Figure
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7-9.
7 Installing Cables
58