3.2 Checking Before Power-On

Prerequisites
Before the power-on, ensure that you have been familiarized with the function and control
relationship of each circuit breaker in the Power Supply and Distribution System. For details
about the function and control relationship of each circuit breaker in the Power Supply and
Distribution System, see the corresponding descriptions in the Container Data Center Initial
Configuration Guide.
Procedure
Step 1 Configure and check the initial parameter settings of the fire extinguishing system by
referring to the Container Data Center Initial Configuration Guide.
Step 2 Check the cable connections of solenoid valves. Disconnect the control cables to solenoid
valves to prevent the fire extinguishing equipment from malfunctioning due to improper
manual operations.
Figure 3-8 Solenoid valve
Issue 01 (2014-3-15)
You have completed the power-on for the Power Supply and Distribution System and the
fire extinguishing power distribution box (PDB) in the container data center.
For details about how to configure and check the parameters, see
Figure 3-8
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
shows the solenoid valve.
3 Power-On Commissioning
3.1 Initial
Configuration.
17