62 Mechanical installation

Bolting together the units

Required bolts are attached to the drive unit side wall adjoining the transformer unit. Align
the units. Then bolt the units together using the 12 hexagonal bolts with 5N·M(see figure
below).

Fixing units to the floor

Floor fixings are not supplied. 16 anchor bolts as illustrated (B in figure below), or screws,
nuts and washers of size M16 are recommended (diameter of holes in base frame: 18 mm).