Ground equipment

Refer to the requirements of national and local electrical codes for the
location. The grounding lug is located on the bottom front of the XFC or
XRC enclosure.
NOTICE – Equipment damage or loss of data. The grounding
conductor must have a cross-sectional area of at least 12 AWG or 4
mm
2
.

Leak-test manifold and tubing connections

Install input lines and manifold.
The following procedure provides a generalized guideline to follow for the
manifold and tubing installation.
Materials:
1.
Stainless steel tubing (length determined by technician)
2.
Four (4) sets of tube fittings, including ferrule and nut pairs
1 8 | XSE RI ES G5 STA RT UP GUI DE | 21 0 60 0 1MNAA