Section 3
Engineering process
20
available information at the time the project is started. This means that several
iterations may be needed to finish the project.
Setting up the PCM600 project
Build the plant structure according to the substation structure.
Insert an IED in plant structure which can be done in many ways. By
inserting the IED in online mode where the configuration is read from the
physical IED, by inserting an IED in offline mode, by importing a *.pcmi
file or by selecting an IED template from the template library (*.pcmt).
Rename the IED objects in PCM600 to the projects definitions.
ACT Application configuration
Configure the protection or control function for example for a transformer
application as requested.
Save the configuration made with ACT to make the interfaces and signals
available for other engineering tools within PCM600, for example for PST.
PST Parameter setting and configuration
Check the configuration parameters of the physical IED for communication
channels, CT and VT conversion values of the transformer module, for
example.
Check and adjust if needed the setting values for example for:
Presentation parameters for local HMI.
Settings for protection or control functions.
Number of setting groups.
GDE Single line diagram configuration
Create a single line diagram.
Include measurements when needed.
Link the dynamic elements to functions created in ACT, for example a
breaker object to the switch function.
Local HMI engineering
Include and engineer the function blocks for LHMI element groups with
ACT.
Configure the function keys and LEDs with ACT.
Define the function key and LED behavior with PST.
Communication protocol engineering
The engineering steps are protocol dependent.
Use the communication management tool (CMT) for DNP3 engineering.
Use the IET600 station configuration tool or the PCM600 IEC 61850
Configuration tool for IEC 61850 engineering. See the application manual
for other protocols (IEC103).
For performance reasons, do not insert more than 150 IEDs
of 650 series type in one PCM600 project. Larger projects
can be divided into several PCM600 projects.