5.3
Introduction
Overview
ÄKTA ready XL Operating Instructions 29281616 AE
TeDIS Valid on Date Printed

Perform flow kit installation test

The flow kit must be tested to verify that sensors and meters are correctly installed
before use. A flow kit installation test method is available for this purpose. A success-
ful test provides an installation report that can be saved as a pdf or printed.
This section describes the procedure of how to test that the flow kit is correctly in-
stalled using UNICORN.
If UNICORN is used as the control software, the installation test method and the in-
stallation test report is found on a CD provided in the delivery.
If other control software is used, refer to the product documentation for an equiva-
lent procedure.
The procedure is performed in the following consecutive steps:
1. Prepare for flow kit installation test
2. Perform the installation test using a dry flow kit.
3. Save and/or print the report
Note:
It is important that the installation test is made on a dry flow kit.
Note:
Priming is performed after the installation test.
Note:
For testing of ancillary filters, mixing tanks and bags refer to the relevant
user documentation for information.
The installation test method runs for approximately 6 min. The sensors and meters
are tested to determine if they are correctly installed. The test contains a number of
questions and test steps. The test is performed without liquid and must be per-
formed on a dry and new flow kit.
When the control software is UNICORN, the steps and the pass/fail results are dis-
played on the UNICORN System Control module screen. The UNICORN Run Log can
be used for troubleshooting.
Note:
In the installation test method, the air sensors and the air trap level sensors
are calibrated when the flow kit and air trap are filled with air. Perform the
calibration of these sensors when the flow kit and air trap are filled with liq-
uid.