Huawei FusionModule1000A20 Commissioning Manual page 39

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
Table 4-4 Auxiliary heater configuration requirements
Position
Pre-fab.
module
Procedure
Step 1 Use a hand-held thermometer to measure the temperature inside the pre-fab.
module. If the temperature reading is lower than 5°C in the pre-fab. module,
perform
Step 2 Start the auxiliary heater to increase the pre-fab. module interior temperature
until it reaches the required normal operating range, otherwise, no heating is
required.
----End
Issue 03 (2022-12-15)
Recommended
Power
2 kW
Step
2.
NO TE
When the auxiliary heater is heating the pre-fab. module, ensure that all pre-fab. module
doors are closed to avoid heat loss and improve the temperature rising speed.
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 Preparations for Power-On Commissioning
Quantity
Deployment
2 PCS
Distributed
evenly in the
aisle.
Prerequisite
The ambient
temperature can
be lower than
5°C.