This section describes operations on a single 15 kVA/20 kVA UPS.
Procedure
Step 1 Install power cables.
Figure 5-1 15 kVA/20 kVA UPS wiring diagram (three-phase input three-phase
output, two power sources)
----End

5.2.2 Starting the UPS

The configured number of batteries on the LCD must match the actual number.
When the actual number changes, change the configured number. If the
configured number is less than the actual number, the battery lifespan is
shortened. If the configured number is greater than the actual number, battery
leakage may cause a fire.
Issue 18 (2021-07-16)
NO TE
For details about how to install cables for the single system, see the
20 kVA) Quick Guide .
CA UTION
Copyright © Huawei Technologies Co., Ltd.
5 Operations
UPS2000-G-(15 kVA–
88

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents