RUGGEDCOM ROX II
User Guide
To launch a link failover test, do the following:
NOTE
The link failover test can be cancelled at any time. For more information about cancelling a link failover
test, refer to
Cancelling the test returns the interfaces to their pre-test condition.
1.
In normal mode or edit mode, navigate to services » link-failover{interface id} » start-test, where
{interface id} is interface to be tested. The Link Failover Test Settings and Trigger Action forms appear.
Figure 714: Link Failover Test Settings Form
1. Test Duration Box
Figure 715: Trigger Action Form
1. Perform Button
2.
Configure the following parameter(s) as required:
Parameter
test-duration
start-test-delay
On the Trigger Action form, click Perform to begin the test.
3.
Testing Link Failover
Section 5.27.7, "Cancelling a Link Failover
1
2
2. Start Test Delay Box
Description
Default: 5
The amount of time (in minutes) to run before restoring service to the main trunk.
Default: 1
The amount of waiting time (in minutes) before running the test.
Test".
Chapter 5
Setup and Configuration