Installing An Ams 2100/2300; Installation Road Map; Unpacking An Array - Hitachi AMS 2100 Hardware Manual

Hide thumbs Also See for AMS 2100:
Table of Contents

Advertisement

Installing an AMS 2100/2300

Installation road map

The following table lists the steps to install an AMS 2100/2300 and provides
links and page numbers where the detailed steps are located.
Step
1
2
3
4
5
6
7
8
9
10
11

Unpacking an array

Observe the following guidelines to ensure your safety. Failure to follow
these guidelines could result in bodily injury or damage to the array chassis
or components.
CAUTION! A fully populated AMS 2100/2300 base unit weighs
approximately 112 lbs (51 kg) and requires three or more people to
lift the array. Before lifting the unit, always turn off the power and
unplug all data and power cables.
An expansion unit weighs 88 lbs (40 kg). Use at least two people to
unpack and install an expansion unit.
Install the base unit at the bottom of the rack. If the array is mounted at
the top of the rack, the rack may become unstable and fall.
5–24
Table 5-3: Installation Tasks
 Unpack the Array
 Remove the front bezel
 Mount the unit in rack
 Turn rack PDBs OFF
 Connect Fibre Channel host cables and LAN cable
 Connect power cables
 Install front bezel
 Turn rack PDBs on
 Turn array power on (front panel)
 Verify that array is ready (check LEDs)
 Install Navigator 2
Installation
Hitachi AMS 2100/2300 Storage System Hardware Guide
Description
Page
5-24
5-28
5-30
5-35
5-40
5-49
5-55
5-49
5-53
6-4
7-13

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ams 2300

Table of Contents