ABB 2 Series Operation And Installation Manual page 55

Table of Contents

Advertisement

Installation
A
C
B
A
B
CAUTION
Make sure that there are no kinks in the cables
The mechanical installation of the EVSE Terra 360 is completed and the electrical connections can be done.
• Move the EVSE (A) on top of the base (B). Use a crane or
a forklift.
• Carefully lower the EVSE on the base. Make sure that
cables do not get trapped between the EVSE and the
base.
• Make sure that the 6 holes in the EVSE (A) and the base
(B) are aligned.
• Open the front door of the EVSE.
• Install the 3 front bolts (D), located on the internal lower
part of the EVSE (in red), to secure it to the base.
• Open the rear door of the EVSE.
• Install the 3 rear bolts (C), located on the internal lower
part of the EVSE (in blue), to secure it to the base.
• Close all doors of EVSE.
D
• Remove the eye bolts (A) on the roof.
• Install the fasteners (B), each with a flat washer and a
split lock washer.
NOTE
To help this operation 2 centering pins are
installed on the base.
NOTE
The fasteners, the flat washers and the split
lock washers are placed in a bag, in the lower
internal part of the EVSE.
55