6.2

Installation of the EVSE - Terra 360 Series 2

6.2.1

Floor space requirements - Terra 360

X1
FRONT SIDE
Parameter
Description
X1
Space to open the left side door
X2
Space to open the right side panel
Y1
Space to open the rear door
Y2
Space to open the front door
NOTE
These dimensions only refer to the required space to open the doors/panels of the EVSE. A
minimum of 1 m extra on each side is required to allow commissioning and maintenance
operations on the EVSE.

6.2.2 Prepare the foundation - Terra 360

6.2.2.1
Prepare the prefabricated foundation - Terra 360
Z1
Z1
Y1
X2
A
Y2
A
A
C
C
B
B
C
C
D
D
Specification [mm]
900
900
1000
1000
• Take the prefabricated foundation (A).
NOTE
Contact the manufacturer to order the
foundation for your EVSE.
NOTE
Refer to
"11.3. Prefabricated foundation -
Terra 60"
for the foundation specifications.
• Dig the pit (B) for the foundation (A).
• Place the foundation in the ground pit.
The front side is indicated by an arrow.
• Leave the foundation 15 mm above the ground level (D).
• Prepare the site and the conduits (C); route the power and
signal cables inside the foundation thought the conduits
appling cable slack of each cable 1000 mm.
• Pour concrete around the foundation to lock in place
the conduits and the foundation itself.