Chapter 6. Installing optional kits

See this section to learn how to install optional kits for ThinkSystem Micro DataCenter 6U 800mm Deep Rack
Cabinet.

Installing the rail kit

Follow the instructions in this section to install or remove the rail kits and servers.
This cabinet supports the following servers and corresponding rail kits. Follow the instructions to install them
into the cabinet.
"Install the rail kit and SE350 E2 Enclosure (2U2N)" on page 19
"Install the rail kit and SR250" on page 26

Install the rail kit and SE350 E2 Enclosure (2U2N)

A A b b o o u u t t t t h h i i s s t t a a s s k k
See the following table to identify the components that come with the rail kit.
1
Document
2
Left rail
3
Right rail
The cabinet supports up to three units of SE350 E2 Enclosure and corresponding rail kit. For optimal use of
space, it is advised to determine the location to install the rail kits based on the number of units that are
installed.
• One unit: 3-4U
• Two units: 2-3U and 4-5U
• Three units: 1-2U, 3-4U, and 5-6U
Note: When installed vertically into this cabinet, the server can be installed with server top facing either right
or left. In this section, however, it is illustrated with the top of server facing right as an example.
© Copyright Lenovo 2020
4
Two M6 screws
5
Four black M3.5 x 5 mm flat head screws with pre-
applied threadlocking adhesive
19

Advertisement

Table of Contents
loading

This manual is also suitable for:

Thinksystem micro datacenter 6u7d2p

Table of Contents