EV Charging Station
½-13 NUT AND ½"
STAR WASHER
CONCRETE
LEVEL
Open the door by pressing the round button on the door latch. Insert the Kiosk from top and install ½-
13 nuts and star washers after lowering skirt over matching threaded rods as shown in Figures 15
and 16.
Torque all the nuts as per the torque specification in Table 1 (recommended tool: 3/8" drive quick
release ratchet and 13/16" socket)
Connect L1 and L2 of circuit 1 and 2 to the fuse block lugs 1 and 2 respectively. Connect ground wire
of circuit 1 and 2 to the ground bar 1 and 2 respectively as shown in Figure 17.
IMPORTANT: EV Charging Station is rated for 208-240V power only. The EVSE must be connected to a
grounded, metal, permanent wiring system, or an equipment grounding conductor. This should be run
with circuit conductors and connected to the equipment grounding bar or lead on the EVSE.
Connections to the EVSE shall comply with all applicable electrical codes and ordinances.
In case of RFID sensor, the communication cable is connected to the Ethernet connector on controller
1 and 2 as shown in Figure 18.