Huawei FusionCol8000-E240 Quick Manual page 6

Modular indirect evaporative cooling system
Hide thumbs Also See for FusionCol8000-E240:
Table of Contents

Advertisement

3.2
Securing the FusionCol8000-E (Building Scenario)
When marking the platform position, ensure that the four lines form a rectangle.
When the equipment is installed indoors, it is recommended that shock pads be installed
between the air duct and the floor.
It is recommended that the strength level of the concrete foundation be at least C20 and
the load-bearing capacity of the ground be greater than or equal to 600 kg/m
1. Determine the area for placing the concrete platforms based on the site and equipment
dimensions, and mark the reference points on the concrete platforms using an ink
fountain and measuring tape.
Separate Installation
Unit: mm
Parallel Installation
Unit: mm
(1) FusionCol8000-E
(2) Concrete foundation
5
.
2