Connecting Water Inlet and Outlet Pipes to the Water-Cooled Module
7.3
Steel Pipe Connection
(1) Reserved port
(2) Steel pipe
8

Installing Cables

1. Power cables and signal cables should be routed according to the requirements for routing
electrical and extra-low voltage (ELV) cables and in compliance with the cable routing plan.
2. The shielding layer of signal cables must be grounded.
3. The outer insulation sheath should be retained when you route a cable through the
waterproof connector.
4. Power cables for the indoor and outdoor units should be bound using cable clips near the
ports of the power module.
5. Shielded cables cannot be used as power cables for outdoor units.
6. The following figures show the dual power supply modes. In single power supply mode, only
QF1 needs to be connected.
8.1
Connecting the Equipotential Bonding Cable
Equipotential bonding point
(1) Needle valve on the
refrigerant side
(2) Needle valve on the
cooling water side
22